Milestone #1 |
Needs Analysis and Requirements Specifications (NARS) |
09/26/2014 |
Milestone #2 |
Project Proposal and Statement of Work (PP and SOW Report) |
10/20/2014 |
Milestone #3 |
System Level Design Report |
11/17/2014 |
Milestone #4 |
Detailed Design Review and Testing Strategy |
02/09/2015 |
Milestone #5 |
Midterm Demonstration in Lab (No Report) |
02/27/2015 |
Milestone #6 |
Final Hardware & Software Demonstration (No Report) |
04/09/2015 |
Milestone #7 |
Final Report |
04/17/2015 |
Budget Overview |
Final Bill of Materials |
04/17/2015 |