TEAM MEETINGS LOG SHEET
Project Name: NASA
(Shih)
Team #: 13
Meeting #: 19
Date: 01/09/2009
Discussions:
- First
Meeting of the Spring
- The
parts finally came in from the purchase orders so the motor, servo, and
raw materials are in
- We
decided to make 3 wing shapes and 3 sizes of each for now in the beginning
stages
- Restated
our schedule
- January:
Construction. All wing assemblies will be made
- February:
Testing and leeway for any problems in construction
- March:
Analyze and more leeway for problems
- We
discussed what labs to use and made meeting times with the “owners” of
such labs
- We
believe that we will not need specialized tools
- We are
sticking with SuperGlue as our adhesive because of its small applicator
and its good properties
- Might
change if the carbon tubes are disagreeable
- Also
if it melts the mylar
- Now
that most of the materials are in, body parts we discussed
- Body:
- Balsa:
easy to access, not as easy to work with
- ABS
plastic and electronic molding: easy to control, could be a bit pricey
- Tail:
- Balsa:
might be unnecessary
- Wire
with mylar in between in 2 different shapes was decided on
- The
control surface will be scavenged
- Track
- Will
be made to allow for easy adjustments to the gear assembly
- Linkages
- Might
cause problems
- Metal:
will ask around for the best material
- Asking
the Magnet Lab, metal fabricators, Keith Larsen
- Rocker
- Will
need a tiny drill
- CAPS
machine shop or the ME machine shop
- The
website was brought up and Parker was helped in brainstorming for things
to include and how to make it more functional and fluid
Deliverables:
- Meetings
with various machine shop people
- Final
set of logs from the fall semester
- The
Restated Spring Proposal and Gannt Chart
Comments/Suggestions:
- For
Monday 1/12:
- George:
- Email
Pics
- Magnet
Lab Micro Machine shop
- Parker
- Dr.
Clark, Keith Larsen
- Pro-E
update
- Website
work
- Brittney
- Gannt
Chart
- Restated
Spring Proposal
- Email
parts to parker
- Josh