SECOND SEMESTER PROPOSAL

The first phase of this project included: Determine shock/spring configuration, analyze suspension geometry, design suspension connection, minimize scrub, write preliminary design report, engineer drawings for each component, analyze composite chassis material, material selection, and ordering parts. The second phase of this project continuing spring semester, includes:

UNFINISHED TASK

  • Finalized engineering drawings
  • New mounting system for the chromoly frame

    IMPROVMENT

  • Better team and group organization.
  • Better work scheduling and time management.
  • Suspension connection: First of all we need to connect the suspension for the double A-arm and bulkhead.
  • Next the engineering drawings need to be done for the suspension and stirring systems.
  • The material for the suspension and the stirring systems is selected depending on the strength and stiffness.
  • Ordering parts for the break assembly needs to be done next. Because without ordering the parts like springs and break assembly the design cannot be carried on to the next level.
  • The forces that the weight of the body impacts to the suspension need to be known. In other words force analysis have to be calculated.
  • The drawings and geometric calculations for the stirring system need to be done either using pro-engineer or AutoCAD.
  • Stress analysis for the composite materials have to be performed before incorporating into the design.
  • The next stage is to test the suspension by performing stress analysis.
  • Analyzing the performance of the suspension is very critical in the design process to check out if any errors occur.
  • Machining the parts for the suspension and stirring systems follows.
  • Finally all the parts need to be assembled.

    Projected Budget

  • Bulk metal (aluminum/iron) 600.00
  • Shocks 1200.00
  • Wheels 1200.00
  • Tires 1000.00
  • Hardware (Bolts/Nuts) 300.00
  • Steering linkage 500.00
  • Steering Box 500.00
  • Brake calipers 400.00
  • Brake rotors 700.00
  • Rotor hubs 800.00
  • Brake lines 200.00
  • Master cylinder 200.00
  • Pedal Assembly 250.00
  • Total 7850.00

    Schedule

    A productive continuation of a project needs a well thought out and organized schedule. This semester’s schedule was actually well though out but not too organized, causing fallbacks in the goals set at the beginning of the semester. However falling short of the desired task to be completed does not mean that they will never be completed. Therefore a new schedule for next semester was thought up and layout in Figure 1 below. This primavera schedule lays out the goals (unfinished task) and the projected timetable on when they will be started and finished. It also has a projected schedule of the solar car team meeting dates. These projected meeting dates are not yet confirmed though.

    Figure1: Second Phase Projected Schedule

    Conclusion

    In conclusion, we have given a basic over view of our problem statement and required task needed to complete the front suspension for Sunsation II. As stated in this proposal the project has moved from phase I to phase II. Phase II of this project is where the design and concept analysis are tested. Although phase I was very productive there was still room for improvement as stated earlier. Our team has looked at the mistakes it has made during phase I, and discussed possible solutions. These solutions will be implemented during phase II, which will help in the quality of our final design.